MILESTONE
Key Events (Green for payments) | Status | Notes | |
Contract Award |
10/27/99 |
||
Completion of Model Testing |
3/18/00 |
||
FEA Model Certified |
5/01/00 |
||
HVAC vender selection |
6/28/00 |
||
Load analysis comp. |
6/14/01 |
||
Cutting of Steel Commences module 3 |
1/8/01 |
||
Keel Laying Ceremony |
2/09/01 |
||
Pro. Motors placed on foundation |
5/02/01 |
||
GFE EM120 transducer frames due |
12/18/00 |
||
Assemble starts module 4 & 6 |
2/16/01 |
||
Land Module 4 & 6 |
5/06/01 |
||
Land prop motor module 5 |
5/02/01 |
||
Land sonar frames module 4 & 6 |
10/28/01 |
||
Land Bow thruster module 1 |
4/20/01 |
||
Weld module19 port (last mod lower hull) |
10/16/01 |
||
Comp. steel work lower hull |
7/24/01 |
||
Land module 21 stbd |
6/09/01 |
||
Land Bow thruster motor |
10/18/01 |
||
Land Die/Gen. sets |
7/23/01 |
||
Land switchboards |
9/27/01 |
||
Land traction winch |
10/11/01 |
||
Land module 34 |
10/16/01 |
||
GFE EM120 electronics & transducers |
10/01/01 |
||
Comp. steel work to main deck |
11/16/01 |
||
Erect module 31 stbd (last mod. set) |
11/1/01 |
||
Substantial comp. of superstructure |
2/22/02 |
||
Vessel launch |
11/17/01 |
11/17/01 |
|
Completion of sea trials |
5/3/02 |
||
Preliminary Acceptance |
6/24/02 |
1/30/02 |
|
Dockside availability (30 day) |
April |
||
Mission trial (30 day) |
May |
||
Available for service |
July |
||
Final Acceptance |
PA + 9 |
6/30/02